Tariff Regulations
West Bengal
The West Bengal Electricity Regulatory Commission has issued the Terms and Conditions of Tariff regulations dated 29th April 2011. The primary purpose of these regulations is to determine of tariff of generating companies, transmission & distribution licensees and SLDC for the year 2011-12 and onwards and Annual Performance Review for the year 2009-10 and onwards.
WBERC Tariff Regulations 2011
Annual Performance Review for the year 2009-10 and onwards.
ii. Switchgear including cable connections- 25 years
iii. Lines on fabricated steel operating at nominal voltages higher than 66 kV- 35 years
b. Depreciation of assets
c. Repair and Maintenance
d. Administrative and General Expense
e. Equity base
f. Man / CKM ratio
[clause 2.5.5]
b. Addition or reduction in the Capital loan
c. Addition or reduction in the Depreciation
d. Addition or reduction in the equity base
e. Taxes on Income, Duties, Levies, cess, etc
f. Non-tariff income
g. Foreign Exchange Rate Variation
h. Interest on Working Capital
i. Insurance premium
j. Effect of rebate / surcharge
k. Income from other business
[clause 2.5.5]
b. Any variation arising out of controllable factors during Annual Performance Review using operating norms, wherever applicable, for determinations of allowable normative expenditure on that factor, shall be on the account of licensee
[clause 2.5.5]
(1) AC system : 98%
(2) HVDC bi-pole links : 92%
(3) HVDC back-to-back Stations : 95%
[schedule 9D clause 2E]
a. Charges for use of network- This component of transmission service charges / tariff shall be reflecting cost of capital investment in and maintenance and operation of, a transmission system to transfer bulk power to and from different locations.
b. System Operation Charges- This component of transmission service charges / tariff shall reflect the cost associated with operating the state load despatch center
The fixed cost of the transmission system shall be computed on annual basis and recovered on monthly basis as transmission charge from the users
The annual transmission Service Charge (Aggregate Revenue Requirement) recoverable by a transmission licensee shall be computed in accordance with the following equation:
AFC = [Gross ARR - NTI - OI]
Where AFC = Annual Fixed Cost
Gross ARR = Gross Aggregate Revenue Requirement of the transmission licensee.
NTI = Approved level of non-tariff income
OI = Approved level of income from other business
Annual transmission service charges shall be recovered monthly. However, the short term customers shall pay transmission charges on a daily basis as laid down in the open access regulations.
[clause 6.16.2]
i) The transmission charge payable for a calendar month for a transmission system or part thereof shall be
AFC x (NDM / NDY) x (TAFM / NATAF)
Where,
AFC = Annual fixed cost specified for the year, in Rupees
NATAF = Normative annual transmission availability factor, in per cent
NDM = Number of days in the month
NDY = Number of days in the year
TAFM = Transmission system availability factor for the month in percent.
The transmission charges shall be calculated on monthly basis according to transmission service charges to be recovered in each month of a year by the transmission licensee.
[clause 6.16.3]
In case of more than one long term transmission customer of the intra-state transmission system, the transmission service charges leviable on each long-term transmission customer shall be computed as per the following formula:
Transmission charges for transmission system concerned and payable for a month by a long-term transmission customer of that transmission system
n
= { ∑ [ AFCi/12 ] - TRSC } X CL/SCL
i=1
Where AFCi = Annual Fixed Charges for the ith transmission project in the transmission system
n = Number of projects in the transmission system concerned
TRSC = Total recovery of transmission charges for the month from short-term customers as specified in open access regulations for the transmission system
CL = Allotted transmission Capacity of the transmission system concerned to the long-term transmission customer.
SCL = Sum of the allotted transmission capacities to all the long-term transmission customers of the transmission system concerned
[clause 6.16.5]
Where, Annual transmission charges shall correspond to intra-state assets and/or for a particular interstate asset, as the case may be
No incentive shall be payable below the availability of 99.75% for AC transmission line and substation system and 98.5% for HVDC system
[schedule 10 clause 8]
[clause 3.14]
b. dated Jul 30, 2013
c. dated Jan 01, 2020
Annual Performance Review for the year 2009-10 and onwards.
[clause 2.8.4.1]
Annual Performance Review for the year 2009-10 and onwards.
[clause 2.5.5]
[clause 2.5.5]
[clause 2.8.4.1]
Annual Performance Review for the year 2009-10 and onwards.
[clause 1.iii]
[clause 8.5.4]